1. Roof deck must be solid
sheathing, either plywood or original plank board construction. Any
large voids must be replaced or covered with sheetmetal.
2. Installation may be applied
directly over rigid insulation board.
3. Overlays are allowed over
original built-up roofing if the roof is in reason able condition.
a. New material may be applied
directly over smooth surfaced or mineral surfaced cap sheet.
b. Gravel or rock surfaced roofs
should be swept clean and covered with minimum 1/2” insulation board
material prior to installation of the new roofing.
4. Severe ponding water problems
should be corrected. (Puddling of water on flat roofs is acceptable.)
Ponding water issues must be evaluated no later than the pre-inspection
or the in-progress inspection.
 |
|
Base Sheet |
3. “Sprinkle mopping” the base
sheet is allowed only over non-nailable decks or instances where nails
are not feasible.
4. Nails should be square head,
ring shanked type long enough to penetrate 3/4” into or through the
deck. Shorter nails may be used to minimize penetra tion of the deck
where visible.
5. Nailing pattern is typically 9”
along each edge with two rows staggered 18” apart down the middle of
the sheet.
C. PLY SHEET APPLICATION:
1. One or more layers of ply sheet
should be applied according to the manufacturer’s specification being
used. Multiple layers may be achieved by lapping the material shingle
fashion.
2. Ply sheets should be solid
mopped with hot asphalt. Edge laps should be 2” minimum. End laps
should be 4” minimum.
 |
| This is a
mineral surface, hot mopped cap sheet roofing system |
D. SURFACE APPLICATION:
1. Mineral surfaced cap sheet may
be solid mopped in with hot asphalt.
2. Gravel may be embedded into a
flood coat of hot asphalt sufficient to cover the underlying plies.
3. Plies may also be surfaced with
asphalt emulsion, Aluminum coating, or other approved elastomeric
coating.
4. Plies must be covered with some
approved surfacing. Leaving plies ex posed is not acceptable.
E. ROOF JACKS AND PLUMBING VENTS:
1. May be reused if in serviceable
condition. When roofing over an existing roof, flashings should be
lifted and installed with the new roofing.
2. Flashings should be set over
the base sheet in a layer of plastic cement and nailed down typically
with roofing nails that penetrate 3/4” minimum into the deck material.
Flashings may also be strip mopped with the plies.
3. The flashing should be primed
with an asphalt primer prior to solid mopping the plies to the flashing
surface with hot asphalt.
4. Plumbing pipes may be sealed to
the flashing with flashing tape, rubber collar, or plastic cement.
F. MISCELLANEOUS FLASHINGS:
1. All vertical angles should
receive a cant strip if the curb is 2 or more inches high.
 |
| A triangular
“cant strip” for verticle angle adherence |
2. Penetration flashings may be
reused if in serviceable condition.
3. All sheet metal penetration
flashings shall be set in plastic cement, nailed securely, primed, and
solid mopped into ply system. Strip mopping flashings into the ply
system may be acceptable with some manufacturer’s requirements.
4. Angles on gravel roofs should
be surfaced with mineral surfaced cap sheet.
5. Top of base flashing should be
nailed securely to prevent slippage.
6. Perimeter edges should be
finished with sheet metal or 3 course minimum with webbing and plastic
cement where applicable.
G. VERTICAL WALL FLASHINGS:
1. Properly surfaced roofing
material may be turned up under existing counter flashing and nailed to
prevent slippage.
2. If the existing wall was
removed, the roofing material may be turned up a minimum 6” into the
wall cavity and new stucco or siding installed over the roofing
material.
3. Properly surfaced roofing
material may be turned up 6” on an existing wall, nailed to prevent
slippage, and sealed with a minimum 3 course using plastic cement and
webbing.
H. EQUIPMENT SUPPORTS AND BLOCKING:
1. All large equipment blocks
and/or sleepers shall be securely mounted to the roof deck and flashed
into the roof membrane in an appropriate way.
2. Conduit and pipe blocking
should not be sealed to the roofing membrane.
I. BUILDING DEPARTMENT INSPECTIONS:
1. Pre-inspection of roof overlays
should be required especially where ponding water is a concern.
2. In-progress inspections should
include spot checks of decking, roof application, and flashing
installation.
3. Final inspections should be
done while the roof is being finished.