|
Modified Bitumen Roofing
A. ROOF DECK:
1. Roof deck must be solid
sheathing, either plywood or original plank board construction. Any
large voids must be replaced or covered with sheet metal.
2. Installation may be applied
directly over rigid insulation board.
3. Overlays are allowed over
original built-up roofing if the roof is in reason able condition.
a. New material may be applied
directly over smooth surfaced or mineral surfaced cap sheet.
b. Gravel or rock surfaced roofs
should be swept clean and covered with minimum 1/2” insulation board
material prior to installation of the new roofing.
4. Severe ponding water should be
corrected. (Puddling of water on flat roofs is acceptable.) Ponding
water issues must be evaluated no later than the pre-inspection or the
in-progress inspection.
B. BASE SHEET APPLICATION:
1. A slip sheet of Kraft paper or
other appropriate material is needed on areas of the deck containing a
large amount of residual asphalt.
2. Nail one layer of base sheet
over the entire roof area.
3. Nails should be square head,
ring shanked type long enough to penetrate 3/4” into or through the
deck. Shorter nails may be used to minimize penetra tion of the deck
where visible.
4. Nailing pattern is typically 9”
along each edge with two rows staggered 18” apart down the middle of
the sheet.
C. APPLICATION OF MODIFIED BITUMEN
ROLL:
1. Apply modified bitumen roll by
use of torch, hot asphalt, or cold process adhesive as required by
manufacturer’s specifications.
 |
| Application of
“torch down” modified bitumen system |
2. The entire roll should be fully
torched, mopped, or glued so that all seams are fully adhered.
3. Edge laps should be 2”
minimum and end laps should be 4” minimum.
D. SURFACE APPLICATION:
1. Mineral surfaced modified
bitumen does not require any further surfacing.
2. Modified bitumen may also be
surfaced with asphalt emulsion, Aluminum coating, or other approved
elastomeric coating.
3. Some applications allow leaving
modified bitumen unsurfaced. IRCC recommends surface treatment of all
modified bitumen roofs.
E. ROOF JACKS AND PLUMBING VENTS:
1. May be reused if in serviceable
condition. When roofing over an existing roof, flashings should be
lifted and installed with the new roofing.
2. Flashings shall be sandwiched
between two layers of modified bitumen. Flashing flange shall be nailed
securely over the first layer of modified bitu
 |
| Flashings set on modified
bitumen |
3. The flashing should be primed
with an asphalt primer prior to installation.
4. Plumbing pipes may be sealed to
the flashing with flashing tape, rubber collar,or plastic cement.
F. MISCELLANEOUS FLASHINGS:
1. All vertical angles should
receive a cant strip if the curb is 2 or more inches high.
2. Penetration flashings may be
reused if in serviceable condition.
3. All sheet metal penetration
flashings shall be primed and sandwiched between two layers of modified
bitumen. Flashing flange shall be nailed securely over the first layer
of modified bitumen.
4. Top of base flashing should be
nailed securely to prevent slippage.
5. Perimeter edges should be
finished with sheet metal or 3 course mini mum with webbing and plastic
cement compatible with modified bitumen.
G. VERTICAL WALL FLASHINGS:
1. Properly surfaced roofing
material may be turned up under existing counter flashing and nailed to
prevent slippage.
2. If the existing wall was
removed, the roofing material may be turned up a minimum 6” into the
wall cavity and new stucco or siding installed over the roofing
material.
3. Properly surfaced roofing
material may be turned up 6” on an existing wall, nailed to prevent
slippage, and sealed with a minimum 3 course using plastic cement
compatible with modified bitumen and webbing.
H. EQUIPMENT SUPPORTS AND BLOCKING:
1. All large equipment blocks
and/or sleepers shall be securely mounted to the roof deck and flashed
into the roof membrane in an appropriate way.
2. Conduit and pipe blocking
should not be sealed to the roofing membrane.
I. BUILDING DEPARTMENT INSPECTIONS:
1. Pre-inspection of roof overlays
should be required especially where ponding water is a concern.
2 In-progress inspections should
include spot checks of decking, roof application, and flashing
installation.
3. Final inspections should be
done while the roof is being finished.
|